WBS+RBS

5 replies [Last post]
divakar babu
User offline. Last seen 15 years 17 hours ago. Offline
Joined: 6 Nov 2009
Posts: 7
Groups: None
How to prepare WBS in road project & how to load the RBS to WBS .please give feed back with exampels

Replies

Rafael Davila
User offline. Last seen 4 days 23 hours ago. Offline
Joined: 1 Mar 2004
Posts: 5241
divakar

If you are into highways planning you should look at Spider Project Linear Diagram, the preferred method to display schedules in highway jobs. Spider Project is the only true CPM software that supports this kind of report while maintaining CPM logic. Other linear Diagram Software are not as good and most do not support resource leveling.

Best regards,
Rafael
What do you mean by loading RBS to WBS?
RBS is Resource Breakdown Structure and groups resources and WBS groups activities.

Do you mean to prepare these strucutures in the concrete software? Then specify the package that you use.

Best Regards,
Vladimir
Shah. HB
User offline. Last seen 1 year 33 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Thanks Anoon
Shah. HB
User offline. Last seen 1 year 33 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
does WBS and RBS goes together in the programme ?
Anoon Iimos
User offline. Last seen 3 years 29 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it is supposed to, however most programs (from what I know) don’t have RBS