Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global WBS or Project Specific WBS

1 reply [Last post]
Richard Day
User offline. Last seen 11 years 7 weeks ago. Offline
Joined: 10 Jul 2008
Posts: 11
Groups: None
In Primavera 6.1 is it better to use a Global WBS or a Project Specific WBS?

I am scheduling about 100 projects with monthly updates.

Replies

Dieter Wambach
User offline. Last seen 7 years 3 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Depends on your needs for reporting.
Internal projects, stakeholders need reports on all projects: Global wbs to e.g. level 2 or 3, more in detail, upon pm’s decision.
Independent projects with different stakeholders: Easier for you with a standard wbs (templates!). May depend on the projects’ stakeholders.