Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Standard Norms?

25 replies [Last post]
Mohd Mahd
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 62
Groups: None
i was wondering, if some standard planning norms is available any where?

Replies

Tomas Rivera
User offline. Last seen 5 years 3 weeks ago. Offline
Joined: 2 May 2001
Posts: 139
Groups: None
Puneet:

Look into the American Welding Society www.aws.org

Tomas Rivera
Puneet Arora
User offline. Last seen 14 years 20 weeks ago. Offline
Joined: 4 Mar 2002
Posts: 4
Groups: None
In case there is a database available with standard norms for welding of pipes and structural steel. Please share the same with us PP’er’s.
Zq qz
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
Gentlemen,
The best thing to do is to track it in your existing project. This is the best way to know this norms , because it varies on different projects and make you more confident in using it.
MMD
Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline
Dear my friends,
They are available on the internet.
Please search with these keywords in the search engine( such as google);

"mil-std"
and
"Project management" or "wbs" or "SOW" or "project risks" and etc

Sample website :
1- www.acq.osd.mil/pm/newpolicy/wbs/wbs.html
2- sparc.airtime.co.uk/users/wysywig/sow_mt.htm
3- www.pppl.gov/me/NCSX_Engineering/SOW/ MIL-STD-245_Guidelines_SOW.pdf
4- www.incose.org/stc/mil499.htm - 85k

Best Regards
Bernard Ertl
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
Mehdi,

I did not see any estimating norms in any of the links you provided. They lay out a specification for structuring the planning, but do not offer any norms for estimating any work.

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
[Duplicate post removed by Moderator.]
Morteza Jafari
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 20 Jul 2003
Posts: 33
Hi Mehdi
I am also intersting to know about the mentioned standard, could you tell us more detailed !
Morteza
Bernard Ertl
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
M.R. - OK. I would be interested in looking at them. How do you find them? Are they available on the internet? Do you have a URL/link to them? Are they available in a print publication? If so, what is the title?

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline
Dear Ertl,
There is standard norms for estimating from military standard.

Regards
M.Rashidi
Ab Halim Hussein
User offline. Last seen 19 years 42 weeks ago. Offline
Joined: 30 Sep 2003
Posts: 3
Groups: GPC Malaysia
i just wonder whether planning planet could gather some info like is there any standard for example
excavation-what machinery we need so on and so forth
well i know it depends on locality but minimum requirement there should be an agreement to it

excavation - excavator (nos depend on output), lorries (etc), bulldozer (needed?) etc

filling - dumper (?) lorries (?) compactor (?) grader (?) etc

if anyone could share some of their experience could be useful to us newcomer
Bernard Ertl
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 20 Nov 2002
Posts: 757
DOD = Department of Defense

However, the DOD does not offer standard norms for planning and estimating as far as I know.

Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline
My friend,
DoD = Dictioanry of Military

Regards
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
What do you mean DOD ?
Mehdi Rashidi Ala...
User offline. Last seen 5 years 37 weeks ago. Offline
Hi,
please see DoD ( or Mil-std-***) standards for PM.

Regards
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
It would be good to have such standards in Planning Planet web page as a seperate link.
Well, this should be used as guideline and all planners to bear in mind the estimates of resourse, duration, cost must largely depended on local or company specific factors.
Ketan Mehta
User offline. Last seen 20 years 19 weeks ago. Offline
Joined: 10 May 2003
Posts: 4
Groups: None
I FULLY AGREE WITH YOUR VIEWS. OUTPUT IS ALWAYS DEPENDENT ON THE OTHER FACTORS BUT STILL WE CAN HAVE THE GENERAL IDEA FOR THE OUTPUT RATES OF THE MOST ITEMS/ACTIVITY. THIS WILL HELP IN OUTLINING THE PROJECT WHEN WE DO NOT HAVE ALL THE REQUIRED DATA. WHILE DETAILING THE PROJECT SCHEDULE, WE CAN CONSIDER THE OTHER FACTORS.

REGARDS
Ahmed Hamada
User offline. Last seen 6 years 1 week ago. Offline
Joined: 5 May 2003
Posts: 9
Groups: None
Dear Sir,
I am supporting strongly the concept that say "every project should be delt as a uniqe case". in the project i am involved in now, we have very big quantities of excavation, the rate of every excavator depends on two major factors,number of trucks serving with, the distance between the site and the stockpiling area and some other minor factors. with the same line we will find this variance in the activities should be done with heavy equipment. so this standard could be useful in some works like blockwork, plastering and some concrete works

regards,
ahmed fouad
Ketan Mehta
User offline. Last seen 20 years 19 weeks ago. Offline
Joined: 10 May 2003
Posts: 4
Groups: None
Its a good idea to have a standerd norms for all the activities.
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
It will be of great help for biginers if some guidelines / standerds / generic norms are available.
WONDERING IF IT IS AVAILABLE ANYWHERE.
REGARDS,
Mike Harvey
User offline. Last seen 10 years 45 weeks ago. Offline
Joined: 6 Mar 2002
Posts: 31
Groups: None
From the time the estimate is prepared and the price for the project tendered the ’Estimator’ should have used some form of ’Performance factor’ possibly taken from ’Spons’or using his own experience.

This should be your starting point, however, most projects are won because somebody in their wisdom wants the project at any cost and the Tender Programme has to then be tailored to suit the necessary requirements of time.

If your project has been awarded under favourable conditions and feed back on rates does not exist in your organisation then you have a problem.

Standard Performance rates(based on Work Study Methods) were a highly guarded secret from the early fifties up to until the advent of ’Management Contracting’.

Some companies still jealously guard this information as it is seen as giving too much away to their competitors.

www.hpcconsult.co.uk are currently publishing their own production rate standard norms to cover all trades.

Whilst some rates are available on the website it will be another 2 years before we attain a full listing of rates.This will then be the nearest to what we see as Standard Norms’ Working conditions/ethics around the world do vary and any rates given must be considered and WEIGHED according to the locality.

An example of this could be-
1)Work force incentive schemes Yes or No?
2)Production slow during Holy Festivals(fasting etc)
3) Poor continuity
4) Poor site management

I hope this has been of some help

Regards
Mike Harvey
Mohd Mahd
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 62
Groups: None
Thanks for the note. they r very useful, in creation standard projects, as well as in evalution, and how u r away from standards. wishing u have further inf about getting any of them! mohd
Ali Vessali
User offline. Last seen 6 years 43 weeks ago. Offline
Joined: 16 Sep 2001
Posts: 55
Dear Sir,
Even you can find such things, you couldn’t use that for all of your project, because each project has its characteristics and you should be care about exact norms or rates for each type of activities.

These rates shall be modified based on the project conditions.

Best regards,
Ali Vessali
Ali Hamouda
User offline. Last seen 7 years 48 weeks ago. Offline
Joined: 3 Feb 2002
Posts: 109
Groups: None
I was searching about such things, If you know something pls tell me? Ali
Mohd Mahd
User offline. Last seen 16 years 13 weeks ago. Offline
Joined: 13 Jul 2001
Posts: 62
Groups: None
thanks for ur reply. YES. yet, i am trying to find the others. and any help will be appreciated.
What do you mean by "Planning Norms" production rates ? James