Overall % Complete

No replies
Jithin Kambhikanam
User offline. Last seen 3 weeks 4 days ago. Offline

Hi All,

Would like to know if we can show overlla % compelete in PRimavera updated schedule.

I have been progress measuring using excel in which some activities progress is measured by

  • Manhours
  • Cost

But the OVerall weightage is claulated based on the assigned weighate as per Contract for example

Engineering - 15%

Procurement - 40%

Construction - 35%

Commissioning - 10%

 

So can we show this in PRimavera 6 updated schedule ?

Regards

Jithin

Rodel Marasigan
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS

david kelly
User offline. Last seen 15 hours 2 min ago. Offline
Joined: 12 Feb 2016
Posts: 33
Groups: None

You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.