Scheduled % complete v/s Activity % complete curve

4 replies [Last post]
Abhijit Suvarna
User offline. Last seen 16 years 4 weeks ago. Offline
Joined: 12 Mar 2008
Posts: 5
Groups: None
could anyone guide me in generating a curve showing the scheduled% v/s activty complete%
regards

Replies

Abdullah Merchant
User offline. Last seen 11 years 26 weeks ago. Offline
Joined: 28 Nov 2010
Posts: 26

Hi,

I am relatively new to planning, and I am currently working on a Project(Clients Side) where I have not loaded any resources. I am currently using MS Project 2007 adn would like to know how to get and S Curve in excell.

Also, I have notice that the baseline dates in MS Project can be chnaged from the column,unlike P6. Is this so or am i missing something here.

niles luo
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
Hi,
I think in this situation PM can not direct show this S curve.Maybe PM can,but I do not know.
My suggestion is
1,Create a resource named A, labor or nonlabor is ok
2,Assign resource A to every activity. The Unit use the default value is ok.
3,Then use the Resource Usage Profile, we can see the Unit Cumulative Curve of resource A. The numuber/total unit is the percent complete.
Maybe above is not a good idea, only FYI.
Abhijit Suvarna
User offline. Last seen 16 years 4 weeks ago. Offline
Joined: 12 Mar 2008
Posts: 5
Groups: None
I want to show the S curve in PM & I have not yet assigned resources
niles luo
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
Hi:
Pls give the further information about:
1,Do you want to show the S curve in PM or the other system just like MS Excel?
2,Do you assign resources to the activities?