Schedule % Complete vs Activity % Complete

5 replies [Last post]
Irfan Khan
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
hi to all,

Can anybody make me understand that what is the difference between Schedule % Complete & Activity % Complete.

Bcz an activity’s activity complete have 6.82% and when i m inserting a column of of Schedule % Complete the same activity showing 9.09%.

so pls tell me logic behind these factors......


thanks in advance......

Replies

Irfan Khan
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
thanks to all.....
Rodel Marasigan
User offline. Last seen 22 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Irfan,
Their answers are all correct. Schedule % Complete is Baseline Planned % (if have baseline) or current Project Planned % Complete (if no baseline assigned) and Activity % Complete is Actual % complete.

The reason why it has 0% on summary bands is because you haven’t cost loaded your schedule. P6 calculation of Progress is based on cost.
Rashid Iqbal
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 7 Apr 2010
Posts: 70
It is the Planned Progress of the Baseline...if as per baseline the activity should have been completed...the ’Schedule Perent’ will show 100%. Thanks.

r
Irfan Khan
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
thanks All

i agree but y it is not showing in total bar...?
Alaa Al haj
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 7 Nov 2007
Posts: 79

Hi
i am not sure but i think activity percent completion is actual progress
while schedule percent completion is the scheduled ( planned progress)


Alaa