Require Activity % Complete equal to Expense % Complete

4 replies [Last post]
Irfan Khan
User offline. Last seen 1 week 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Hi to all experts,

 

I am using Primavera P6 R8.2

 

Here i am working with the schedule with 4,000 activities & almost 2,200 activities i have loaded Cost though Expenses.

The Problem i am facing that for example : one activity having 50% of  Activity % Completed so far, but when i am looking @ the Expenses Tab & its not showing me any actual cost for the same activity. Even i have tried to Import & Export throuhg excel in order to reflect the Activity% complete into Expenses % compete but due to (*) sign the values in exel sheet cant be modified.

 

Please anyone can help me in this regard.........i will be highly obliged  

 

Replies

Irfan Khan
User offline. Last seen 1 week 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

Thank you Mr. Zoltan.......... i got what i was looking for.

Zoltan Palffy
User offline. Last seen 2 days 19 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2990
Groups: None

no the global change suggestion will not work you can not cross % complete between activites and expenses even is you create a UDF

I have supplied the solution here

http://pmsite.com/forums/viewthread/3203

 

Irfan Khan
User offline. Last seen 1 week 6 days ago. Offline
Joined: 19 Jul 2009
Posts: 138

i tried to resolve it through Global Change......but unfortunately i didnt get way to fix it.... :(

Ahmed KHR
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Hi Irfan,

 

Try to use global change (Expense % = Activity %)

 

Regards