Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

On Same Data Date Actual Units Doesn't Equal Cum AtCompletion Units

3 replies [Last post]
rauf kensuk
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 28 Dec 2019
Posts: 7
Groups: None

Hi All,

Once a week, i update and schedule my P6. This week I noticed that some of activities' Total Actual Units doesnt Equal for the same week Cum At Completion Labor Units.

In my case they all should be the same, I think (Because my Budgeted Labor Units equals At Completion ( there s tiny difference that I avoid)

In English name of the Activities

-Rough Construction Works (CW)
-Interior CW
-Facade CW
-Mechanical CW
-Electrical CW
-Escalator CW
-Elevator CW
-Landscape CW

 

Data Date 22.Aug.21
First Day of The Week is Monday

Percent Comp. Type is Unit
Duration Type is Fixed Duration&Units

7888
resim_2021-08-24_102724.png

wysiwyg_imageupload::

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

that will do it

rauf kensuk
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 28 Dec 2019
Posts: 7
Groups: None

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.

rauf kensuk
User offline. Last seen 1 year 44 weeks ago. Offline
Joined: 28 Dec 2019
Posts: 7
Groups: None

I found the problem. Some acitivities in progress have 0-zero- Rem duration. This causes a problem.