Activity % complete and Schedule % complete

2 replies [Last post]
Vrinda M
User offline. Last seen 3 years 43 weeks ago. Offline
Joined: 8 Jun 2008
Posts: 24

Dear all,

 

Please help urgently as I have program in P6 which needs to be updated weekly.

But from last 2 weeks Iam updating the program in P6 howver the activity % complete is not changing and schedule % complete is changing and showing increase.However the Activity % is not showing any change,.

 

What could be the reason for this???

 

Rgds,

Vrinda

0507641002

Replies

Neeraj kumar
User offline. Last seen 9 years 1 week ago. Offline
Joined: 24 Sep 2011
Posts: 2
Groups: None
Dear Vrinda, Activity percentage completion type is "Duration" in your project. You shall change the "Type" among Duration-Units-Physical.
  1. Choose Project, Activities.

  2. Select the activity whose percent complete type you want to define.

  3. Display Activity Details, then click the General tab.

  4. Select the percent complete type:

    To indicate that the activity's percent complete will be entered by the user for this activity, select Physical. In this case, Activity % Complete = Physical % Complete.

    To specify that the activity's percent complete be calculated from the original or planned and remaining durations, select Duration. In this case, Activity % Complete = Duration % Complete = (Original or Planned Duration – Remaining Duration) ¸ Original or Planned Duration.

    To specify that the activity's percent complete be calculated from the actual and remaining units, select Units. In this case, Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).

walid Lahiani
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning,

I looked for your question,I found in the net that:

There are many different methods for calculation of actual progress in Primavera P6.  These methods involve using many fields and settings, including:

  • Duration % Complete
  • Units % Complete
  • Physical % Complete
  • Percent Complete Type
  • Activity % Complete
  • Performance % Complete
  • Earned Value settings of the WBS Elements

So may be you are showing in your column an other percent complete different of the percent complete of your global project

 

Good luck