Hello Fellow Planners,

 

I was wondering if the activity steps are linked to activity complete at all?

 

In order to clarify my question, I would like to give an example:

If my activity has 3 steps (same weight assumed-> 0,33) and I check one step as completed, the activity has a progrss of 33%. Will this progress be transferred to the activity complete (status tab in activity details), as well? also, does this transfer depend on the activity percenet complete Type?

 

I have tried to accomplish the challenge mentioned above, but it seems that I have to transfer the activity step complete % to the activity % complete field manually.

I would be glad to hear from you!

Thank you very much!