Duration% Complete X Units % Complete

2 replies [Last post]
Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear all,

A frined of mine has this doubt:

Can Duration%Complete (for Activity progress) be different of Units%Complete (for Resource progress on activity)??

In my opinion, it can be different. Activity progress can be proportionally different of Resource progress. By the way, it normally happens.

Any different opinion??

Regards,

Marcio Eduardo.
Rio de Janeiro - Brazil.

Replies

Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Kevin,

Thanks for your interest.

Best regards.

Marcio Eduardo
Rio de Janeiro - Brazil.
Kevin Button
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Marcio

It certainly is possible (and often necessary) to have Duration % and Units % working independently. In project view, select the Calculations tab and make sure the box titled "Recalculate Actual Units and Cost when duration % complete changes" is NOT ticked.

You will still need to define a suitable default % complete type for your activities (either duration, units or physical) but you can display the columns for each of these % types in the activity view.

Regards