difrence between orignal duration & at completion duration

2 replies [Last post]
rizwan khan
User offline. Last seen 10 weeks 4 days ago. Offline
Joined: 28 Aug 2012
Posts: 11
Groups: None

Dear all

 I had problem with the duration which i was working , there is 

 

 

 

what is diffrence between orignal and at copletion duration , how we can use it  in primevera 

thanks you all

Replies

Arnold Puy
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Hi Rizwan,

The Original duration is the number of working days required to complete each activity based on the current schedule. However, At completion duration is the sum of the actual duration and the remaining duration.

Cheers,

Arnold

rajesh kumar
User offline. Last seen 10 years 39 weeks ago. Offline
Joined: 14 May 2013
Posts: 3
Groups: None

hi

Orginal Duration -planned duration 

at cmpt duration nothing but  actua work performed during project