Report - Manhours Planned Vs Actual

3 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 3 weeks 2 days ago. Offline

Hello Everyone,

 

I have made a resource loaded schedule. 

I am looking for report which can Show me Planned Manhours (As per Basline) and Earner Manhours (After Updating the Schedule) and Remianing Manhours (After Updating the Schedule) in Time Distributed Format like below,

Item06-Jan-1913-Jan-1920-Jan-1927-Jan-1903-Feb-1910-Feb-19Total
Baseline       
Earned       
Remaining       

 

Experts please give me your input.

 

Regards

Jithin

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

check you email here 

Jithin Kambhikanam
User offline. Last seen 3 weeks 2 days ago. Offline

Hi Zoltan,

I dont have such a report RE-01. Is it done other report. Could you guide me please.

 

Regards

Jithin

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

canned report in P6

RE-01 Earned Value Units for WBS and Activities