Forum Sponsor:
Tips on using this forum..
(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?
(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.
Report - Manhours Planned Vs Actual
Wed, 2019-03-13 08:56
Hello Everyone,
I have made a resource loaded schedule.
I am looking for report which can Show me Planned Manhours (As per Basline) and Earner Manhours (After Updating the Schedule) and Remianing Manhours (After Updating the Schedule) in Time Distributed Format like below,
Item | 06-Jan-19 | 13-Jan-19 | 20-Jan-19 | 27-Jan-19 | 03-Feb-19 | 10-Feb-19 | Total |
Baseline | |||||||
Earned | |||||||
Remaining |
Experts please give me your input.
Regards
Jithin
Replies