Hello Everyone,
I have made a resource loaded schedule.
I am looking for report which can Show me Planned Manhours (As per Basline) and Earner Manhours (After Updating the Schedule) and Remianing Manhours (After Updating the Schedule) in Time Distributed Format like below,
Item | 06-Jan-19 | 13-Jan-19 | 20-Jan-19 | 27-Jan-19 | 03-Feb-19 | 10-Feb-19 | Total |
Baseline | |||||||
Earned | |||||||
Remaining |
Experts please give me your input.
Regards
Jithin