S Curve Manhour- Baseline , Actual , Forecast

5 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 1 year 5 days ago. Offline

Hello Everyone,

 

I would like to make a S Curve in Primavera which shows Planned, Actual and Forecast S Curve.

The basis of S Curve to be manhours / Week.

Can S Curve in Primavera show % Planned per week as Lables like in Excel.

I want to calculate the S Curve which shows end of the Week Palnned % and Actuals (Not start)

Please guide me.

 

Regards

Jithin

Replies

Zoltan Palffy
User offline. Last seen 13 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

NOTHING show the label you did not ask for the label 

Jithin Kambhikanam
User offline. Last seen 1 year 5 days ago. Offline

Hi Zoltan,

But that doesnt show % Planned Label per Week. 

 

It shows the curve but doesnt show the label.

Regards

Jitin 

Zoltan Palffy
User offline. Last seen 13 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage spreadsheet

Jithin Kambhikanam
User offline. Last seen 1 year 5 days ago. Offline

Hi Zoltan,

 

I am looking for a s curve which would be like this showing lables.

 

7355
capture.jpg

Zoltan Palffy
User offline. Last seen 13 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

create a resource

assign the resource to the activities

assign the proper manhours to each activity

view show on bottom resource usage profile

select the cureves that you want to show