Adding Manhours after Baseline is Set

1 reply [Last post]
Vaughn Edwards
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 1 May 2008
Posts: 16
Here we go....After I set a baseline and begin to excute the schedule we have FCO’s (field change orders) issued which add extra manhours to the schedule. How can I enter these hours without affecting my Planned Baseline hours.
I run a report which shows Original Hours, FCO hours, and Hours to Completion. I need this report to show the FCO hours added to the Completion column.

Replies

Rodel Marasigan
User offline. Last seen 18 hours 52 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Vaughn,
You can use Resource Code or Activity Code or UDF to identify Original Hours and FCO hours and group & sort by those codes you selected to use.

Another approach is using a separate WBS for FCO activity.