Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Adding Manhours after Baseline is Set

1 reply [Last post]
Vaughn Edwards
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 1 May 2008
Posts: 16
Here we go....After I set a baseline and begin to excute the schedule we have FCO’s (field change orders) issued which add extra manhours to the schedule. How can I enter these hours without affecting my Planned Baseline hours.
I run a report which shows Original Hours, FCO hours, and Hours to Completion. I need this report to show the FCO hours added to the Completion column.

Replies

Rodel Marasigan
User offline. Last seen 15 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1516
Vaughn,
You can use Resource Code or Activity Code or UDF to identify Original Hours and FCO hours and group & sort by those codes you selected to use.

Another approach is using a separate WBS for FCO activity.