Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

HOW TO DEVELOP A REVISED BASELINE SCHEDULE, LAST UPDATE SCHEDULE?

1 reply [Last post]
abubakar munir
User offline. Last seen 1 year 12 weeks ago. Offline

Dear Professional,

Hope every one is fine.

Let me first put up my case, I have updated schedule up to August 2017 (Schedule % 17.5 & Performance % 15.2) at that time.I received an approved EOT of 40 days from a consultant I revised my schedule with respect to fast track/crash method technique to overcome the delays.
Now the issue is that when I go to remove the old baseline to assign the new one(copy of revised schedule) at that time my schedule% & performance % value drop down to zero by removing the (Project Baseline).

I normal conditions our Performance% complete will be now our schedule % complete after revising the schedule for future tracking & monitoring.

Your earliest response is required

Regards,
Abubakar

 

Replies

Zoltan Palffy
User offline. Last seen 18 hours 22 min ago. Offline
Joined: 13 Jul 2009
Posts: 2432
Groups: None

try running a global change 

where planned start equals start 

and planned finish equals finish