Assigning last month updates as baseline for this months updates

2 replies [Last post]
Girish Bhave
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 16 May 2013
Posts: 10
Groups: None

Dear All,

Whenever i assign last project updates for current month baseline all the actuals till last months updates gives wrong dates. It creats lots of confusion whenever i wanted to compare the current status with the last months status.

Please help me if anybody have the solution for this problem.

Thanks & Regards,

Girish Bhave

 

Replies

Girish Bhave
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 16 May 2013
Posts: 10
Groups: None

Dear Mohsin,

Thanks for sharing , It realy works. 

Regards,

Girish Bhave

Kaif Mohsin
User offline. Last seen 2 years 50 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Dear Girish,

Go to the Admin, Admin Preferences, Earned Value Calculation Settings and change it to "Budgeted values with current dates"

This will show you the actuals from the last month updates when it is assigned as a baseline to the current month update.

Best Regards,

Kaif Mohsin