Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS Start and Finish Date in P6 schedule

2 replies [Last post]
Vignesh S
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

Anyone Kindly guide me on how to display start and finish date at WBS lvl in P6 schedule printout.

Replies

Vignesh S
User offline. Last seen 7 years 13 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

Thanks Jerome,that worked out nice

Jerome Odeh
User offline. Last seen 3 weeks 21 hours ago. Offline
Joined: 19 Jan 2004
Posts: 102

Vignesh,

From your menu bar, click on View > Group & Sort and in the Group & Sort dialog box, tick "Show Group Totals" check box under Display Options. Click Apply and then OK.

 

=jerome