Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned Dates = Start and Finish Dates

1 reply [Last post]
Richard Hill
User offline. Last seen 15 years 43 weeks ago. Offline
Joined: 31 May 2006
Posts: 4
Global Change in P6 is not as easy as it used to be (i.e. in P3)

For the life of me I can’t seem to get the parameters to say - Planned Start = Start and Planned Finish = Finish. I mean, come on the logic is simple enough then why can’t I find any parameter to say just that!

Thanks

Replies

Richard Hill
User offline. Last seen 15 years 43 weeks ago. Offline
Joined: 31 May 2006
Posts: 4
Apologies no need for reply back.
I figured it out in the end! Wasn’t what I expected but I entererd
Start is Greater than or Equal to PS and
Finish is Less than or eEqual to PF
> Then Planned Start is Equal to Start and
Planned Finish is Equal to Finish.