Finish to Start Relationship -Lag =0; Predecessor finish date and successor start date is same

3 replies [Last post]
prabu deva
User offline. Last seen 13 years 1 week ago. Offline
Joined: 31 Jan 2007
Posts: 8
Groups: None

I have prepared a schedule in P6 with activities having finish to start relationships after scheduling the the finish date of the predecessor activity and the start date of the successor activity remains same while the start date of the successor activity should be one day after the finish date of the predecessor,what may be the likely problem in P6 settings please advice

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

there are 10 items to check 

item #1 as stated by Alexandre check your TIMES turn them on by selecting Edit, User Preference, then select the Dates tab at the bottom under Time select 12 hour and show minutes

item #2 Also check you durations in the users preferences click on the Time units and under Durations Format make sure that the decimal is 2 places. If you have ANY original durations or remaining durations that that are not whole numbers change these to whole numbers.

item #3 check ALL constraint dates for the start constraints make sure that the start TIME is 8:00 am or the earliest time in anyy of your calendars being used.

item #4 check ALL constraint dates for the finish constraints make sure that the finish TIME is 5:00 pm or the end of the latest time in anyy of your calendars being used.

item #6 make sure that your Project START TIME is 8:00 am or the earliest time in anyy of your calendars being used.

item #7 make sure that your project must finish by date TIME is correct the finish TIME should be 5:00 pm or the end of the latest time in anyy of your calendars being used.

item #8 for any activites that are in progress make sure that the actual start date TIMES are correct that the ACTUAL START TIME is 8:00 am or the earliest time in anyy of your calendars being used.

item #9 make sure that the data date TIME is correct make sure that the start TIME is 8:00 am or the earliest time in anyy of your calendars being used.

item #10 if all of these are correct then select tools then schedule then options then at the bottom where it says calendar fir scheduling Relationship Lag select Successor Activity calendar. theses are the only things that can affect this.
Henry Hermosura
User offline. Last seen 6 years 31 weeks ago. Offline
Joined: 11 Sep 2017
Posts: 6
Groups: None

Hi Alexandre, what if you are using more that one calendar work days how to fix this 

Predecessor finish date and successor start date is same? Any idea?