Planned cost calculation Error

1 reply [Last post]
pulkit verma
User offline. Last seen 4 years 41 weeks ago. Offline
Joined: 11 Jul 2014
Posts: 10

Hello All,

 

In P6 EPPM 8.3, While calculating planned cost as = Planned qty  * Price per unit , Price calculated automatically is coming incorrect there is variation in Price.

There is only One price/Unit for resource I have checked the dates also for the same.

P6 is picking price from EBS master data after sync but in that Its looking fine

Please revert as soon as possible

 

Regards

Pulkit Verma

Replies

Zoltan Palffy
User offline. Last seen 6 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that on your resource is is not set to claculate costs from units