Spot the difference in two Primavera update

6 replies [Last post]
Amjad Hanan
User offline. Last seen 6 years 28 weeks ago. Offline
Joined: 17 Jan 2015
Posts: 4

Dear Gents, 

We used to send primavera update to our planning manager on weekly basis. Is there any provision in primavera to spot the difference in progress for the only activities from the previous week.   

Your help in this concern is unfathomable! 

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

it appears that you do not have java either installed or enabled 

Amjad Hanan
User offline. Last seen 6 years 28 weeks ago. Offline
Joined: 17 Jan 2015
Posts: 4

Thank you Mr. Kannan and Mr. Eoin , It works! 

 

@Zoltan, Is claim digger an add-in option in primavera? When I select claim Digger, it retrieve a mesage "The selected application: C:\Program Files (x86)\Java\jre7\bin\javaw.exe cannot be found." have experineced any issue as such ?

 

Eoin Flannery
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 29 Jul 2015
Posts: 7
Groups: None

+1 for using baselines.

We would use an original baseline to display the Rev0 then use a second bassline as a copy of the previous weeks issue.

A trick we use is to save each weekly issue as a baseline (witht the issue date) but dont have it displayed.

So in essence we have 3 "live" basleine with each issue.

1: Original Rev 0

2: Last weeks basline

3: Copy of issue (not displayed)

 

Each week we issue the shcedule we would simply change the copy of last weeks baseline.

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

why not use claim digger ?

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

why not use claim digger ?

Kannan CP
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Amjad,

Set the last week project as the baseline for this week update. Create the filter to show the baseline dates for the previous week. compare it against the present update.

I hope this will help