Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revised baseline having two different schedule percent complete for the same data date

No replies
Akbar Shahabudeen
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 25 Jun 2011
Posts: 3
Groups: None

Hi Everybody,

The MBSL was prepared and approved before 2 years & it worked fine. Recently my Master Baseline schedule (MBSL) was asked to revise due to Extension of Time. I revised my MBSL by inserting new milestones & corresponding links also been changed.

Now my Problem is, when I start to update i get 2 different schedule percent complete for the same data date.

ie., on extracting the monthly cashflow in revised baseline I computed the monthly planned value. when I attach it to the updated schedule with actuals by making a copy of revised baseline report I get different value, not as same as planned value obtained through cash flow. But i hope it should match

There was no change in resource assignment only links have been changed.

Please help me to fix this issue

 

Best Regards,

Akbar