Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Activity Suspension

7 replies [Last post]
Abilash Palakkada...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Hi guys, In P6 8.1, I found something strange with activity suspension; when I have updated the schedule with DD – 14/Feb/14 I found one activity to be suspended from 28/Feb/14 till 15/Mar/14. After entering the suspension and resume dates, when I reschedule the activity moves and it shows that the remaining job to be performed only after 15/Mar/14 onwards. It doesn’t shows the work to be performed between data date and suspension date (14/Feb/14 ~ 28/Feb14). This is affecting the resource distribution as well; have any of you experienced this? Advise if you have any suggestions to fix / get rid-off this problem. Regards, Abilash

Replies

Tom Reichner
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 23 Nov 2011
Posts: 46

For the suspend-resume activity, keep following the predecessors back until you find a relationship that eliminates the suspend-resume situation when you change the relationship. The newer versions of Primavera seem to be more sensitive to continuity of the start-finish relationships in a path. 

Ravi Katare
User offline. Last seen 11 years 13 weeks ago. Offline
Joined: 14 Jul 2014
Posts: 23
Groups: None

Hi Abhi,

- If the suspend/resume functionality is used then the early start is set equal to the resume date, its design for work in this     way only .

Also you should know; - The early finish is calculated using the resume date and the remaining duration.- If the suspend date is entered without a resume date then, P6 ignores the suspend date.- Units and costs are not spread over the period of suspension.- P6 calculates an actual duration for all activities based on the amount of non-suspended time.- The amount of time that an activity’s progress is suspended is generally deducted from the total duration. - Ravi
Nima Sadeghi
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 13 May 2014
Posts: 2
Groups: None

Hi Abilash / Mike,

 I'm also experiencing the same issue! I checked all the settings and calendars and it still shows inactive period between the datadate and suspend date. Is yours resolved or you still have the problem? Please help / advise.

 

Regards, Nima 

Abilash Palakkada...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47
Hi Khaja, There is no constraints or any driving relationships. Br Abilash
Khaja Sharief
User offline. Last seen 11 years 35 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

Please check if there any constraints imposed and activity relationships.

Abilash Palakkada...
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 25 Aug 2012
Posts: 47

Hi Mike, Both calendars are active during 14/Feb/14 ` 28/Feb/14

 

Br,

Abilash

Mike Testro
User offline. Last seen 47 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Abilash

Check your calendars both on the task and resource allocations.

Best regards

Mike Testro