Level of effort activity’s actual progress
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
That means there is no built-in function in P6 to do it ??!!
Use a Global Change
You will need to use 2 action statements, one to do the Actual/At Completion part and then another to multiply this result by 100 to arrive at a percentage value.
Thanks. But in this case I need to manually calculate the progress every time I update the schedule
My target is to set the level of effort activity to automatically calculate progress as follows:
Activity % Complete = Actual duration / At Completion duration.
Is there a way for that? How?
Change the Percent Complete Type to Physical