Applying Progress to a Level of Effort Activity

3 replies [Last post]
Philip Richards
User offline. Last seen 14 years 46 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 29
Groups: None
Can anyone please advise.

I am trying to update the ’Actual Units’ to a Level of effort activity in P5. Units go in ok, and Remaining units & percent complete do change accordingly, but when the project is re-scheduled, Actual units go back to zero.

I have Duration Type set to ’Fixed Duration & Units’ & Percent complete type set to ’Units’. There is no curve applied to the resource.

Regards

Phil

Replies

Philip Richards
User offline. Last seen 14 years 46 weeks ago. Offline
Joined: 7 Jan 2004
Posts: 29
Groups: None
Thanks guys.

Both of your contributions were helpfull in resolving my problem.
Jim Fairchild
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 17 Mar 2003
Posts: 10
Check your Project Preferences under the Calculations tab. If you are entering Actual Units manually you need to make sure that the "Recalculate Actual Units and Costs when the duration % changes" is unchecked.
Dieter Wambach
User offline. Last seen 7 years 2 hours ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Phil,
actual units and level of efforts does work in P3e. There should be a mistake.
Some questions:
- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesn’t produce your situation.
- Did you create correct relationships (SS then FF)?
- Did a resource report actuals as well - via Timesheets?

Sorry, no answer, just more questions

Dieter