Can anyone please advise.
I am trying to update the Actual Units to a Level of effort activity in P5. Units go in ok, and Remaining units & percent complete do change accordingly, but when the project is re-scheduled, Actual units go back to zero.
I have Duration Type set to Fixed Duration & Units & Percent complete type set to Units. There is no curve applied to the resource.
Regards
Phil