Level of Effort Activity Type
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Thanks. Ill do some more test, especially the combination on relationship type.
I did extensive testing when writing my Primavera Enterprise book and it worked with my system.
I have also just checked again and I can confirm a LOE may work the same as a Hammock but may also work differently depending on the relationships used.
Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers
www.eh.com.au
I cannot work out the span from the finish of activities to the start of activities for a LOE in P3e/c!! I dont know why.
It always behave a hommack as P3
A Hammock in P3 and SureTrak will only span from the Start of one or more activities to the Finish of one or more, and therefore spans a period when work takes place.
IN PE a LOE will span from the finish of activities to the start of activities which was not possible with P3 & SureTrak. Therefore may span a period when there are not activities scheduled.
I hope this clarifies things.
Paul E Harris
Eastwood Harris Pty Ltd
Planning and Scheduling Book Publishers
www.eh.com.au
Thanks, I know this one already. According to manual "Move P3 to P3e/c", if more than one predeccessor and succesor assigned, the ES of LOE is latest ES dates and EF of LOE is earliest LF dates.
I do some tests on P3e/c v3.5, cannot work out what described in manual, the result always same as hommack, ie ES of LOE is earliest ES dates and EF of LOE is latest EF dates.
Am I miss anything any setting?