Adnan Amjad
User offline. Last seen 18 years 18 weeks ago. Offline
Joined: 10 May 2005
Posts: 8
Groups: None
I want to show the suspension on activity due to rain more than once in a week but in P3 u can show suspension of an activity only once have anyone got the solution.

Replies

Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi David

Put it on the calendar as non work days.

Best regards

Mike T.

David Burrows
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 12 Oct 2006
Posts: 5
Groups: None

I have a project that has 3 periods of total suspension that needs to be built into the schedule.  

Each period will be for a minimum of 14 days and while the suspendion of work is known ahead of time, the project period does not include the 42 days involved.  

Is there a way to show the planned 14 day work suspensions without the time accruing against the total project time? 

 

THANK YOU FOR YOUR ASSITANCE. 

 

David R Burrows

Steven Oliver
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
If you have a need to retain the information, I would suggest that the most effective method would be to add new activities to describe the delay. In this way demonstration of the effect is much clearer and easily understood.

HTH
Adnan Amjad
User offline. Last seen 18 years 18 weeks ago. Offline
Joined: 10 May 2005
Posts: 8
Groups: None
Right, for rainy days Calander holidays are most effective but if suspension is for any other reson effecting only that perticular activity more than once then is there any other alternative available then defining a new separate calander for that perticular activity.
Paul Silver
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 30 Sep 2004
Posts: 16
Adnan,

Consider modifying your calendar to reflect the rain days.

Regards
Paul Silver