Project Controls Engineer, ARCONS, Alkhalij Power Plant - Sirt Libya

START Date: 
December, 2009
END Date: 
July, 2012

• Reviewing and studying contract agreement.
• Preparation of Method Statement for Erection of steel structure and tanks.
• Preparation of master and detailed project schedule (Primavera P6).
• Updating and follow up project schedule.
• Preparation of Daily, Weekly & Monthly Progress Reports.
• Preparation and follow up Material Control System.
• Control and follow up of monthly payments.
• Coordination and control of all incoming and outgoing e-mails and letters from and to the client.

PLANNING COORDINATOR, Mancon Consutlancy and Project Management , Mantrac Takoradi New Facility-Ghana

START Date: 
July, 2012
END Date: 
June, 2013

* Preparing master and detailed time schedule (using primavera P6 and MS Project).
* Coordination with design team to prepare tender package
* Evaluation and awarding of contractors.
* Preparation of contract agreements complying with FIDIC standards.
* Preparation of projects budget.
* Following up construction phase (time and cost).
* Coordination with different project parties (emails - meetings).
* Document controlling (project documents - historical data - lessons learned)

Practice Director, Project Partners, LLC, Primavera Consulting

START Date: 
January, 2000

Experience in

1. ERP system like Oracle E-Business Suite

2. Project Management system like Primavera, @Task, Microsoft Projects

3. Other tools like Primavera Unifier, Instantis EnterpriseEtrack, P6 Analytics, BI Publisher, Oracle Business Process Management to name few  

Planner engineer, eni - petrobel, All Onshore and Offshore Projects

START Date: 
October, 2013

current job : planner enginner at petrobel company

previous job : civil engineer for 6 years  2003-2009

                    site manager for 2 years  2009 - 2011

                    project manager for 1 year 2011 to 2012

                    Planner engineer  for 1 year 2012 - 2013

all my experience years in oil and gas  field 

Planning Engineer, Desein Pvt Ltd, Viyawada Thermal Power Plant

START Date: 
July, 2010
END Date: 
October, 2013

Company Name

Blue fence Pvt Ltd

Duration

From : Jul 2010

To:  Dec 2010

Designation

Planning Engineer, Desein Pvt Ltd, Viyawada Thermal Power Plant

START Date: 
July, 2010

Company Name

Blue fence Pvt Ltd

Duration

From : Jul 2010

To:  Dec 2010

Designation

Assistant Planner, Laing O'Rourke Australia, Wheatstone LNG Plant

START Date: 
August, 2013

Our company is responsible for all the concrete and civil works of the ISBL and OSBL areas of the LNG plant.

Planning Manager, GMR Energy Limited, 2X685 MW GMR Chhattisgarh Energy Ltd.

START Date: 
August, 2010

Project Management, Planning & scheduling, Primavera P6, MSP, Contract Management 

Planning Manager, GMR Energy Limited, 2X685 MW GMR Chhattisgarh Energy Ltd.

START Date: 
August, 2010

Project Management, Planning & scheduling, Primavera P6, MSP, Contract Management 

Planning Manager, GMR Energy Limited, 2X685 MW GMR Chhattisgarh Energy Ltd.

START Date: 
August, 2010

Project Management, Planning & scheduling, Primavera P6, MSP, Contract Management 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content