Artemis 7000

Planning Engineer, Lothian Regional Council, General Maintenance of Lothian Region Water & Drainage

START Date: 
June, 1992
END Date: 
February, 1995

Provision of the day to day planning for maintenance and emergency repair of the water and drainage services.

Experience Hours (Planning & Scheduling): 
3000

Planning Engineer, BOUYGYUES OFFSHORE, UBIT EXPANSION PROJECT

START Date: 
July, 1990
END Date: 
December, 1994

Planning assistant for the OSO CONDENSATE FIELD PROJECT (2 years and 1/2) : Planning set-up and following, monthly report (partially). Member of a consortium. Project is 0.5 billion of dollars, part of BOUYGUES OFFSHORE is 100 MUSD.
Planning Enginner for the UBIT EXPANSION PROJECT (2 years) : full planning set-up and following, monthly report, leader of the consortium of 2 members, coordination of the 4 mains contractor for planning purposes. Project is 200 MUSD, part of BOUYGUES OFFSHORE is 120 MUSD.

Experience Hours (Planning & Scheduling): 
3000

Planning Engineer, CLC Gestion de Projet & Conseil, Various National & International Projects

START Date: 
January, 1995
END Date: 
July, 1998

- ALSTOM TRANSPORT : Set-up of a resource management system for the ATS department (Automatic control Transportation System) of the Signalling buisness.
- ETPM (Now ACERGY) : For EKPE revamping project (125 MUSD budget, full revamping of MOBIL EKPE installations),set-up of the marine operation planning, and follow-up offshore (9 month in Nigeria). Project was used to confirm work hours estimation methods.
- ALSTOM TRANSPORT : Bid Planning manger for Porto Metro project bid (PORTUGAL) and JFK (New-york) automatic subway.

Experience Hours (Planning & Scheduling): 
7000

Scheduler, Fabricom, BPA General Electrics

START Date: 
November, 1986
END Date: 
August, 1987

Artemis 2000 and Artemis 7000 scheduler.

Construction schedule for chemical plant (plastics, extruders), Location Bergen op Zoom, Netherlands

Start of scheduling career is in the year 1986
Experience Hours (Planning & Scheduling): 
1800

Scheduler, Fabricom, BPA General Electrics

START Date: 
November, 1986
END Date: 
August, 1987

Artemis 2000 and Artemis 7000 scheduler.

Construction schedule for chemical plant (plastics, extruders), Location Bergen op Zoom, Netherlands

Experience Hours (Planning & Scheduling): 
1800

Senior Planning Engineers - Artemis 7000, Wimpey Construction, Teesside Power (Enron Operations)

START Date: 
March, 1991
END Date: 
August, 1992

Responsible for the maintenance of the detailed project network to support all aspects of the construction of a 1875MW Gas Fired Power Station (comprising 8 Gas and 2 Steam Turbines)  The project covered all phases of site activity including:

  •               Undertaking all planning activity involving developing bespoke system amendments/reports.
  •               Major project elements planned included Civils and Structures, Mec

Senior Planner, Foster Wheeler France, EXXON POLYETHYLENE AND POLYPROPYLENE PROJECT

START Date: 
August, 1990
END Date: 
February, 1992

 

 

  • 1990 - 1992 FOSTER WHEELER, FRANCE

SENIOR PLANNING ENGINEER

POLYETHYLENE & POLYPROPYLENE PLANT

 

Developed a Level 3 Schedule and integrated reporting system on Artemis 7000, with automatic generation of Level 2 and Level 1 schedules and progress curves, and reporting to the client, Exxon.