Newfoundland and Labrador (NA.CA.NF)

Planner/Scheduler , Pennecon Energy, Hebron GBS Project

START Date: 
July, 2013
END Date: 
July, 2014

Responsible for development, control and monitoring of titanium and 6Mo pipe fabrication schedule for Exxon Mobil’s Hebron project. Updating and tracking progress against baseline and reporting on the outputs. Other duties include creating fabrication workpacks, coordinating the coatings process and shipping to ensure timely site delivery. Deputised for the Project Manager during business and vacation absences.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
300

Project Controls, Pennecon Energy, Long Harbour Processing Plant

START Date: 
August, 2014
END Date: 
March, 2015

Led the on-site project controls function; including developing the multi-disciplinary construction schedule, updating progress, monitoring against baseline, tracking changes, developing recovery plans, drafting change requests, preparing reports using Earned Value techniques and producing KPI reports and S-curves. Also, managing labour, equipment and materials resources to ensure efficient flow of work was maintained.

Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
600
Experience Hours (Forensic Analysis): 
300

Jeff Lloyd

First Name: 
Jeff
Last Name: 
Lloyd
  • Planning & scheduling
  • Cost control
  • Project management
Change management
Professional Since: 
Sep-2003 (20.6 yrs experience)
Oldest experience: 
Jul 2013 (10.8 yrs experience, WARNING: 9.8 years variance with Professional Since)
Years Experience: 
3
Guild Accreditation: 
GPC Member

Planner/Scheduler, NL Hydro, 230kV Transmission Line & Substations

START Date: 
May, 2016
END Date: 
July, 2017

Develop and maintain project master schedule for construction of a new transmission line. Analysis and integration of contractor schedules. EV analysis, both SPI and CPI. Identification of project risks. Tracking procurement items. 

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
500

Planner / Scheduler, Transocean, Various capital projects

START Date: 
March, 2009
END Date: 
October, 2011

800x600

Russell Sacrey

First Name: 
Russell
Last Name: 
Sacrey
  • Participate in the development of all levels and complexities of esti

Professional Since: 
Jan-1996 (28.3 yrs experience)
Oldest experience: 
Jan 1996 (28.3 yrs experience)
Years Experience: 
22
Guild Accreditation: 
Awaiting Applicant

Senior Estimator, Cahill Group, (various projects)

START Date: 
October, 2017

Fill lead estimating and cost engineering role

Generate project controls plans, processes and procedures aligned with industry best practices.

Experience Hours (Planning & Scheduling): 
50
Experience Hours (Cost Management): 
450

Planner/Scheduler, NL Hydro, Various

START Date: 
April, 2015
END Date: 
May, 2016

Planner/Scheduler

Resonsible for development, maintenance, monitoring and control of project schedules for various projects throughout Newfoundland and Labrador. 

Experience Hours (Planning & Scheduling): 
2100

Team Lead, Planning & Scheduling, NL Hydro, All Regulated Capital Project

START Date: 
August, 2017

Team Lead Planning & Scheduling

Leading group responsible for planning & scheduling activities within NL Hydro Engineering Services Division.

Experience Hours (Planning & Scheduling): 
650

Sasan Golnaraghi

First Name: 
Sasan
Last Name: 
Golnaraghi
Professional Since: 
Sep-2002 (21.6 yrs experience)
Years Experience: 
0