Senior Project Controls Manager, PARSONS BRINKERHOFF, California High Speed Rail Program


START Date: 
October, 2012
END Date: 
November, 2013

Responsible for managing the California High Speed Rail Authority Program Controls Department which included estimators, cost engineers, schedulers and document control staff. Provided day to day project controls support and reporting to successfully provide for California’s transportation future. Provide and implement an integrated system of project controls and reports to manage the $63.4 billion dollar program using a variety of tools including MS SharePoint, Oracle Primavera P6, Oracle Primavera CM 14 and Arc GIS.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1000

Senior Project Controls Manager, Laing O'Rourke, Atlantis the Palm and Al Raha Beach Development, Dubai Air Airport T3

START Date: 
March, 2004
END Date: 
March, 2012

1.       Take part in the sitting up of the PMO

2.       Developing controls for the Gateway methodology and its related process

3.       Development and implementation of the core control and integration tools e.g. standard WBS, Chat of Accounts, Work Package List, standard BOQ dictionary and business information breakdown structures

4.       Development and implementation of the programme reporting dashboards

Senior Project Controls Manager, SNC Lavalin, Al Wedyan Township Programme

START Date: 
November, 2016
END Date: 
July, 2018

Senior Project Controls Manage at SNC Lavalin.

Managed and developed the master plan programme for Al Wedyan maste deveelopment in KSA.

Experience Hours (Planning & Scheduling): 
350
Experience Hours (Cost Management): 
350

Senior Project Controls Manager, Brown & Root, Petrochemical Plant Construction

START Date: 
March, 2017

Senior Project Controls Manager

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
1050
Experience Hours (Forensic Analysis): 
300

Senior Project Controls Manager, Schema Management Group, 15 GE frames F Open Cycle Oil Power Plant project

START Date: 
May, 2008
END Date: 
May, 2009
Senior Project Controls Manager for Qurayyah - 15 GE frames F Open Cycle Oil Power Plant project (BEMCO - Saudi Arabia & Lebanon) – 2.2 billion SAR. PMC responsible for BEMCO (as main contractor) Project Management in the preparation and implementation of proper Execution Plan, project procedures an methodologies, project schedule, cost control, communication, document control, change orders management, risk management, contract administration, progress monitoring, recommending corrective and preventive actions and reporting. The team was composed of approx. 30 people.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
900
Experience Hours (Forensic Analysis): 
250

Senior Project Controls Manager, GE, Utilities

START Date: 
January, 1998
END Date: 
January, 2001

►     General Electric, Houston TX , 1998 to 2001 (LS Projects)

Project Manager. Profit/loss responsibility and had oversight/management responsibility in design, fabrication, construction, TA and startup of power plants. Projects delivered in Oklahoma, New Jersey, Texas, Brazil, Colombia, Uruguay, and Panama. Representative projects:

Senior Project Controls Manager, Global Industries & SBM, Oil & Gas Gulf Coast, South America & Africa

START Date: 
February, 2001
END Date: 
February, 2004

►     Global Industries Ltd, Sulphur, LA, 2001 to 2004(LS Projects)

Senior Project Controls Manager, Jacobs Engineering, Several

START Date: 
January, 2008
END Date: 
January, 2011

Senior Project Control Manager. Government security cleared to work on nuclear projects.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
2000

Senior Project Controls Manager, Stantec Consulting Ltd. , Potash Underground and head Frame Expansion

START Date: 
January, 2014
(Potash Corporation of Saskatchewan, Vale Canada, BHPB Billiton, KGHM Victoria, Mosaic Potash, Cayeli Bakir Isletmelari A.S., Red Lake Goldcorp Inc., Glencore Canada Corp.,Lake Shore Gold Corp.) This position is responsible for providing leadership and quality assurance to the project controls activities of the Stantec Mining Practice, the project controls team and client. This position performs a wide variety of project controls tasks, ranging from complex to routine, all of which contribute to efficient and professional operation of the Mining Practice.
Experience Hours (Planning & Scheduling): 
600
Experience Hours (Cost Management): 
7200
Experience Hours (Forensic Analysis): 
10000

Senior Project Controls Manager, Stantec Consulting Ltd. , Potash Underground and head Frame Expansion

START Date: 
January, 2014
(Potash Corporation of Saskatchewan, Vale Canada, BHPB Billiton, KGHM Victoria, Mosaic Potash, Cayeli Bakir Isletmelari A.S., Red Lake Goldcorp Inc., Glencore Canada Corp.,Lake Shore Gold Corp.) This position is responsible for providing leadership and quality assurance to the project controls activities of the Stantec Mining Practice, the project controls team and client. This position performs a wide variety of project controls tasks, ranging from complex to routine, all of which contribute to efficient and professional operation of the Mining Practice.
Experience Hours (Planning & Scheduling): 
600
Experience Hours (Cost Management): 
7200
Experience Hours (Forensic Analysis): 
10000