Sub-contract Senior Project planner
Freelance planning for Bridges Ltd AMP 6 & 7 water treatment work
EPCM Planner & Providing planning support to over 10 Project managers in the Kent area.
 Develop & agree with PM and Site Manager a project Work Breakdown Structure
 Develop & agree with the PM and Site Manager Scope build methodology & sequence
 Develop draft build programme (high level build sequence & methodology): Break scope of works down i.e.
systems / services and fit into WBS developed

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
550

/ Construction Project Planner / Senior Planner, Crown House Technologies (Laing O'Rourke), LD4.2

START Date: 
January, 2018
END Date: 
April, 2019

Lead MEP Project Planner
Have been involved in building data centres from concept to soft hand over on 60mega watts
Projects in slough, London:
 Assist project planner in updating the MEP section of the programme based on the latest design (post tender
design) information
 Discuss and help project planner in setting up regular reporting, production reports, KPIs to allow the site
team to understand the project position in relation to current progress

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

/ Construction Project Planner / Senior Planner, ALPHA CONSRUCTION, & Power infrastructure works and 132kv/66kv substation distibution station

START Date: 
March, 2019

The Bicker Fen substation is the new substation which processes the electricity generated by the onshore wind farm. The power is then fed into the National Grids’ existing Walpole Substation. Alpha was contracted to construct civils elements of works to the client’s design. Our works included the construction of numerous piled foundations, super grid transformer bunds, a control building which includes a steel structure with composite cladding walls and roof complete with internal blockwork partitions and full M&E installation.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300

/ Construction Project Planner / Senior Planner, Simplex Infrastructures Limited, Various 2/4/6 laning NationalhIGHWAYS pROJECTS

START Date: 
March, 2011
END Date: 
July, 2012
  • Preparation of fully resource and expense loaded Baseline Construction programme in Microsoft Project 2010 with 15000+ activities.
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Prepared & presented monthly reports to top management in monthly project meetings.
  • Prepared resource optimization report.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Preparation of Delay tables, Productivit
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
250

/ Construction Project Planner / Senior Planner, Larsen & Toubro (L & T) Limited, 000ft2 Office Building

START Date: 
July, 2012
END Date: 
October, 2013
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Evaluates the impact of changes on cost, schedule, operations and scope documents.
  • Participate in meetings with Project Managers and provide schedule related input.
  • Prepared & developed L2 & 3 Level Baseline construction programme in P6.2 & updating the same on weekly basis.
  • Record and
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

/ Construction Project Planner / Senior Planner, John Sisk & Son Ltd, Travelodge Hotel

START Date: 
August, 2018
  • Preparation of fully compliant Tender programmes.
  • Preparation of Baseline programme fully resource loaded in ASTA Power project.
  • Delay analysis & producing time impacted programmes.
  • Producing resource loaded programmes for tender submissions.
  • Updating programme with progress in ASTA (Straight/Jagged line)
  • Producing revised construction programmes.
  • Subcontractor co-ordination.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500