Civil construction planning engineer, CNE –INVEST CERNAVODA , CERNAVODA UNIT# 2 NUCLEAR POWER PLANT

START Date: 
April, 2003
END Date: 
January, 2006

APRIL 2003-JANUARY 2006

Company/Institution: AECL (CANADA)-ANSALDO(ITALY) - SNN BUC(ROMANIA)CONSORTIUM -PROJECT MANAGEMENT TEAM

Plant Place: CNE –INVEST CERNAVODA UNIT# 2 NUCLEAR POWER PLANT

Position: Civil Construction Planning Engineer

Duties:

  • Prepare the integrated schedules using the information received from Engineering, Procurement and Construction departments.
  • Establishing, monitoring and controlling the Level 2 and 3 Project Schedules.
  • Advise on matters that could prevent meeting p

Civil construction planning engineer, Joannou & Paraskevaides, Pearl Qatar, Qanat Quartier

START Date: 
July, 2008
END Date: 
December, 2010

Creation of Master Programme, Updating, Monitoring of Site Progress and Reporting. Instigation of financial data in to the program and subsequent analysis.

Evaluating Subcontractors Programme and Progress Monitoring

Preparation of Supporting Document for Extension of time Application and other related Claims.

Civil construction planning engineer, Al Futtaim Carillion, AL RAHA DEVELOPMENT

START Date: 
June, 2004

Senior Planning Engineer

 

  • Establishing and preparing the tender program (CL 14) by Co-ordinating with Project Manager/Director.
  • Establishing and preparing the Contract/Baseline/target programme for all projects and continually updates the current work progress to keep the team and management aware of changes to the schedule and possible consequences.
  • Assess & Evaluate Construction Methods & technique.
  • Checking & Approving Subcontractor Programmes.
  • Making of Progress Reports, for Both Management

Senior Planner engineer, Assistant Planning Engineer, Civil construction planning engineer, Agip KCO,Bechtel international, Japan Gas Co. Corporation (JGC-Japan), "Bechtel, Technip, Fluor Daniel, Tecnimont, Lurgi & Linde", Roads %26 Infrastructure, Power

START Date: 
August, 1990

Establish and manage effectively a planning and progress control system in order to support the Project Manager's decision-making process and allow him to complete the project according to the internal baselines and in compliance with the contractual dates and requirements. Ensure any deviation from plan is promptly spotted and analyzed, final time impact is estimated and the effect of corrective actions taken is monitored. Create a schedule awareness atmosphere among all project participants.