Asta Powerproject

Using Formula answer in another Formula

Hi all,

Does anyone know how to / if you can refer to an answer of a formula in part of another formula?

If you can, could you please explain how?

Kind Regards,

 

Chris

Show duplicate items for multiple assignments in PP10

Hello,

Asta Powerlines April 2012 (http://www.astadev.com/asta-powerlines-april-2012/asta-powerproject-hints-tips-april-2012/) features an instruction on how to sort your multiple assigned library codes. Step 2 of 'Sorting where multiple codes are assigned' shows an option to 'Show duplicate items for multiple assignments'.

Network Diagrams

I know somebody is going to come along and say "just press this button", but where can I view Network Diagrams

 

Ronan

Tables

Hello

I'm using v12 and have created a table for a progress report.

How do I copy / import this table into another programme? The table definition doesn't seem to appear in the library explorer....

Any help gratefully received to avoid having to type out all the formula again...

Thanks

Abby

User defined field - not showing unless i put a date on the chart

Hi there

Made a user defined field via "User Field Manager" called Frequency, all I want to type in there is "Monthly" or "2 yearly" or "Weekly" etc.

I've added it to my chart, I type in the activity description as usual, I type in the "Frequency" column the frequency but when I move off the column onto another, I lose whatever is in the "Frequency" column - unless I draw a date on the gant chart.

I've had this problem before, and Ive sorted it, but that was about 2 year ago and I now cant for the life of me work out how to have whatever is in my user defined columns

Effort & Modelling

While putting a programme together, I often use "Effort & Modelling". This obviously enables me (or rather the programme) to calculate durations. So I model, get a duration and then save eveything as a baseline.

However the quantities change, and so to do the durations. I now want to show on two seperate columns

1 The baseline quantities

2 The new quantities that gave new durations

I've been told that you cannot do this on Asta, that instaead I have to use a "user defined field" , and type in manually all the new quantities.

Re-Schedule

I have been given a programme to review. It Asta V12. When I re-schedule, I find 2 tasks that have

  1. No Links (in or out)
  2. No constraints of any kind

After I re-schedule (F9), the tasks “just sit there”. They do not move back to the re-schedule date. I can “move” them to another date, and again they just sit there. What is causing this??

Ronan

Resource leveling is Asta

Dear all,

I just downloaded the trial version of Asta Easyplan and was playing around with it. So far neither in menus nor in help file could I find a resource leveling option. Can somebody help me to pint out to the right place?

I am looking for what is MS Project is done by Tools=>Level Resources and in Spider is called Resource Constrained Scheduling 

import from excel to PP

Hi

1-is it possible to import data from excel to powerproject, i am not speaking about copy and past.

2- when you import a baseline to the current project, how the two programs are related, are they linked using the activity id ?

 

regards

mimoune

Can Asta withstand progress updates done on the different dates on the different tasks?

Dear all,

I am coming from Microsoft Project world (which a lot of people consider not a proper scheduling tool) and I am looking now for alternatives.

I have a discussion about Spider Project tool functionality on this forum.

http://www.planningplanet.com/forums/spider-project/530450/tracking-progress-spider#comment-75696