impacted program on p6

2 replies [Last post]
Amir Mina
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 9 Jul 2007
Posts: 4
Groups: None

 

Dears I need urgent answer,

1-In breif and steps how can i do impacted program on p6 ?

2- Should I updated whole activities or just only which I have to show their delay

 

Please help me quickly

Replies

Shah. HB
User offline. Last seen 18 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Amir Mina

 

Have you finalized the method you are going to asses the delays or to calculate the impact of delay event,only then detailing of procedure can be further discussed in this forum.

 

In you are using simplest method Impacted as planned , then you don't need to update the program

Cheer's

Shahul

Mike Testro
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Amir

It doesnt matter waht software you use the principle is the same.

1. Create a list of delay events.

2. Establish the programme tasks that are affected.

3. Work out the actual impact date of the event.

4. Create a task that represents each event and link up using FS link.

5. Reschedule and note the delay effect - if any.

6. Go on to the next event.

Impacted Delay Analysis only works if the work is ongoing.

Therefore use the original contract programme before any progress.

The system is as good as your programme - constraints - SS FF Links - lead lags - will distort the results.

Best regards

Mike Testro