I have this predicament.
Our project is delayed and it was only acknowledged by the client thus giving the contractor a TE. The TE was issued on let's say March 31st 2012. The contractor submitted a schedule (they called it revised schedule and we were expecting it to be a 'revised schedule') on April 7th 2012. However, the data date of the submitted revised schedule is 30th of November 2011, which was the date of their impacted schedule they submitted last year.
1) I argued with the contractor why they did submit a revised schedule with the date, he said issuance of EOT is not an event thus.
2) They said they were not willing to change anything with the revised schedule as it based on the original approved baseline.
3) They just don't want to re-submit a revised schedule based on the status when the EOT was issued.
Dear Planners, I would really appreciate your comments on this. I have the firm stand that they should have submitted the revised schedule based on the latest status when the EOT was issued.
Thanks in advance.
D'Artagnan
Replies