Hello All,
Good day. I need your opinion and inputs. Our contractor already behind of schedule and the Client asked them to prepare a Recovery Plan. Now, we had already approved the contractor’s Baseline Programme.
In order to catch up the delayed of the project and to meet the milestone date, Contractor made a recovery plan with subsequent action plan, includes changes of construction method, method statement, augment site organization and additional resources in order to improve the quality of works.
During their submittal in P6 Format they changed the sequence, remaining duration, logic, and etc…
My question is, is it possible for the contractor to omit or delete some of the activities from the baseline programme which they to used to developed for recovery plan?
The approved baseline schedule has a total of 4,198 activities and the recovery plan they submitted was reduced to 4,172 activities. The 26 numbers of activities has been deleted.
Regards,
Arnold
Replies