Can't get P6 to assign Baseline dates

J
John Kelly 👤 Member for 14 years 10 months

Hi folks,

I searched the forums for an answer to this and couldn't find anything hence the new post.

I have multiple programmes, A baseline and monthly updates. 

I have assigned the monthly update of March as a baseline to the April update, (reason being i want to show alippage against previous month rather than against baseline)

I have added the baseline as usual using the 'maintain' function then assigned as Primary baseline, problem is though that the planned dates (BL1) aren't showing as the dates that i can see when i look at the March programme, i think its taking the dates from the original Baseline somehow.

 

Anybody any ideas?

 

Thanks in advance

R
Raymund de Laza 👤 Member for 16 years 6 months

John,

Open March Program and perform Global change by equating Planned Dates = Start and Finish dates then assign as baseline to April. This will give you what you requires.

Hope this will help.

Forum Sponsor

Top Posters

Lee Mallek
23 posts
Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts