Creating Baseline in Primavera P6

3 replies [Last post]
Rajesh Passi
User offline. Last seen 12 years 23 weeks ago. Offline

Good Morning everyone, I had a quiery in P6 releated to Baseline.

1. How to assign baseline?

2. How to maintain baseline?

3. How to do update progress in assigned baseline? 

Replies

Ahmed KHR
User offline. Last seen 7 years 18 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

The probleme is about the Planned dates (P6 consider Basline planned dates and not START/FINISH DATES)

Ahmed KHR
User offline. Last seen 7 years 18 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Hi Rajah;

 

You can assign baseline by the steps below:

1-Project=>Maintain baseline=>Add (the baseline).

2-Project=>Asign baseline=>select the project wich u have already maintain it in the 1st step.

3-Go to View=>Bars and display the project baseline bar.

Its easy to do it but I have a problem!!!!

The finish date of the activities already started don't correspond to the project wich I choose as Baseline???????!!

Thank you for yours help.