Create a Filter that show activities with no baseline

3 replies [Last post]
Mike planner
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hi, 

 

I want identify all the new activities i added to my original programme. 

In order to do that, i think i need to create a filter that shows all the activities with no baseline but i cannot find a solution. 

How do i create a filter that show all the activities with no baseline?

 

Thanks

Mike  

Replies

Mike planner
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Thank you so much!

 

Mike 

Rafael Davila
User offline. Last seen 19 weeks 6 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241

Also of interest is when I need to identify and show all activities in compared schedule but absent in current version.

Absent-in-compared-schedules-Gantt

Santosh Bhat
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 15 Apr 2005
Posts: 381

Use a filter with condition "Where BL Project Start (or BL Project Finish) Equals" and leave the value field blank.