Gannt chart showing logic between baseline activities

1 reply [Last post]
John Wilson
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 6
Groups: None

I am using P6.7 and have copied and pasted with a base line a very simple schedule, which seemed to work ok

When I view the current schedule with baseline and also the logic links the logic is between the baseline activities.

Has anyone seen it before and what was the solution

Rgds John

Replies

John Wilson
User offline. Last seen 11 years 17 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 6
Groups: None

Sorted it

If the baseline bar has higher priority that the remaining bar the logic will go to the baseline activities