How to show multiple baselines on bar chart area

1 reply [Last post]
Ahmet Tuter
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 7 Feb 2013
Posts: 50
Groups: None

How can we show multiple basines on barchart area? and up to how many baselines can we show, in addition (under) each actual bar?

Replies

Zoltan Palffy
User offline. Last seen 3 days 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1588

u can show 3 

1st go to project maintain baseline then choose it 

then go to assign baseline and select the one that you just chose to maintain.

Do this for the Primary baseline

the Secondary basline 

and the Tertiary baseline

then go to bars and check the box next to each of these descriptions

make sure to put each of these bars on a seperate row or they could be show on top of each other