Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Multiple Projects in one Integrated Schedule - How to show baselines in Gantt Chart

5 replies [Last post]
Heather Hadley
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None

Hi All,

 

I have created an integrated schedule with LOEs from Start and Finish Milestones in individual projects (a total of 35) by externally linking the LOE in the integrated schedule with the milestones in the individual projects. 

 

My problem is that I want to show on the Gantt Chart the LOE created for that scope in an individual project as well as a basline bar from that individual project.  For example, Start / Finish Milestones were Jan 1 and Jun 1 in the baseline.  Now they are Jan 15 and Jun 2 in the current schedule which is what my LOE will show.  How do I show the Jan 1 and Jun 1 as a bar in my gantt chart with the LOE bar?

 

And, just to make it even more complicated, is there a way to show an earlier baseline in there as well - say the project has originally baselined the dates as Oct 31 and Mar 7.  Is it possible to show the current LOE bar, the Jan 1 to Jun 1 baseline bar and the Oct 31 to Mar 7 bar all on the same gantt chart.  I've been trying to mess around with the Assign/Maintain baselines but am getting frustrated....

 

Any help is greatly appreciated!!

Thanks

Heather

Replies

Zoltan Palffy
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

glad i could help 

Heather Hadley
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None

I like this!  Thanks!

Zoltan Palffy
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

if you are just showing LOE then do this

copy the project

filter where activity type not equal to LOE

next deleted all these activiites (all you are left with are the LOE activities)

now change all of the Actvitiy type to Task Dependent

for all of these add a primary constraint START ON and make the date equal to the planned start date 

for all of these add and expcted finish constraint equal to whatever the date was originally

recalcute the schedule chnanging the data date to whatever the baseline data date was 

now go into your current schedule select Project Maintain Baselines and selet Add and select the project you just created

now selet Project assign baseline and select the project that you just created

now filter where activity type eqauls LOE

now right click in the gantt area and select bars

in the bar setting make sure to show the Primary Baseline bar 

DONE 

Heather Hadley
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 29 Jan 2019
Posts: 27
Groups: None
Excellent!! I was going down that line but wanted validation before I spent too much work. Thanks!! Greatly appreciated!
Santosh Bhat
User offline. Last seen 12 weeks 1 day ago. Offline
Joined: 15 Apr 2005
Posts: 381

In P6, each project requires its own baseline project (set under PROJECT>MAINTAIN BASELINES), and then you have to one-by-one for each project select which is the Project, Primavera, Secondary etc. baseline project.

Bear in mind that baselines are displayed by comparing Activity ID, you need the same ID in both the current and the baseline project for the baseline bar/milestone to be displayed.

In your example, if all your LOE's and and milestones are in one single project anyway, you could just create baselines of this one project with each of the LOE/Milestones showing the "past" date you want to show.