Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Creating the baseline in P6

1 reply [Last post]
Miguel Rios
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 10 Oct 2009
Posts: 18
Groups: None
How do you create a baseline in P6? I know the approach is different from P3 in which you create a target a file and then make a separate file for your current schedule.

Replies

Dieter Wambach
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Step1: Project --> Maintain BL --> Add ...
Step2: Project --> Assign BL

Read the manual for the difference between Project- and User BL

Good luck!
Dieter