(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Opening 3 projects and create a baseline of them all

5 replies [Last post]
Ron Beechey
User offline. Last seen 1 day 13 hours ago. Offline
Joined: 13 Apr 2016
Posts: 24
Groups: None

How do I create a single baseline of the 3 projects that reflect the 3 open together?   Is it a baseline for each project and just update it or can I do it all at once while they are all open?

Replies

Zoltan Palffy
User offline. Last seen 2 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2335
Groups: None

you can show 3 baselines and the current schedule at the same time

when you select the bars just make sure to put the 3 different baselines on different row numbers so that if the dates over lap one bar is not drawn on top of the other. 

Ron Beechey
User offline. Last seen 1 day 13 hours ago. Offline
Joined: 13 Apr 2016
Posts: 24
Groups: None

Thanks all for the help I think I understand the issue now.  I will have to work around the fact that I really can't show all the baselines at once.   I was mainly interested in major milestones committed to by the contractors and having the ability to show the slippage and the downstream effect while having them as stand-alone plans that I just import into to update.

Zoltan Palffy
User offline. Last seen 2 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2335
Groups: None

you can have up to 3 different baselines associated with one project. 

Alexandre Faulx-B...
User offline. Last seen 5 days 2 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1243

Hi Ron,

I am not sure Zoltan answered your question.

When you open several projects, you cannot select all the projects together in the Project, Maintain baselines dialog box; you need to select one project at a time and therefore create individual baselines; however, it is not necessary to close the dialog box between two projects

Should you nedd absolutely to have only one baseline for several projects, the only way in my opinion is to merge the projects by cut/paste the activities from one project to the other, very easy to do when the projects are open together

Alexandre

Zoltan Palffy
User offline. Last seen 2 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2335
Groups: None

when you assign a baseline the project can not be open and once it is assigned it wil become hidden from view until your restore it if you decided to do so.