Moving EPS Nodes

1 reply [Last post]
khosro Shakron
User offline. Last seen 11 years 30 weeks ago. Offline
Joined: 27 Aug 2012
Posts: 2
Groups: None

Hi all,

We have a discussion here about who moved a specific EPS node in P6 from its original location to a wrong place... Company Admin refers to Audit table which shows an Update on the node by project superuser and his interpretation is that update means move. At the same time, update could be other things happening under the node... Any idea would be highly appreciated.

Regards,

Khosro

Replies

Khaja Sharief
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44

One impact of moving EPS  will be change in summarization of data at its parent EPS node.