Limit Layout to EPS Node

1 reply [Last post]
Hugh McLeay
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 12 Mar 2012
Posts: 20
Groups: None

Hello,

I'm just wondering if there's a way to limit access to certain layouts when working on a project in a particular EPS node.
E.g. I have different EPS Nodes for Client programmes, My programmes, and Subbie programes.
I also have different layouts (specifically different title blocks and logos for printing).

I'd like to make it so that I can't accidentally apply a Subbie layout to a Client programme and hence print it with incorrect title block and logos etc.

Thanks,

Hugh.

Replies

mimoune djouallah
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

Hugh

i avoid this situation by adding a prefix to the global layout for example:

Client1- three weeks look ahead

Client 2- three weeks look ahead etc

it would be nice if  we can group  layouts by EPS

 

regards

mimoune